Camas High School

The Camas High School remodel was completed in 1996.  The renovations to this high school boost the quality of school moral and education to the building which was originally built in 1957.  Classroom were refurbished, along with the commons area, senior lounge, and a new student store . There were improvements to the HVAC system, an enclosed weight room and separate wrestling room.

Size: 114,100Sq. Ft.
Project Cost: $5,553,000
Construction Cost: $4,431,000

Project Address

1612 NE Garfield
Camas, WA 98607

Picture of Camas High School

Architect:

DLR Group

General Contractor:

Berschauer Phillips Construction Co

Client:

Camas School District 117

CSG Services Provided:

View Complete Program List »