La Center K-8 School

9This project consisted of four phases to modernize and expand the existing K-8 campus. The project was a complete remodel inside and out of service upgrades to current codes and use levels. Included were new classrooms, new roof for the existing facilities, paving of the bus barns, new kitchen equipment and expansion of the cafeteria.

Size: 106,830 Sq. Ft. (35,607 Sq. Ft. New - 71,223 Sq. Ft. Mod)
Project Cost: $12,963,000
Construction Cost: $10,801,867

Project Address

700 E 4th Street
La Center, WA 98629

Picture of La Center K-8 School

Architect:

LSW Architects PC

General Contractor:

Triplett Wellman Inc.

Client:

La Center School District 101

CSG Services Provided:

View Complete Program List »